土方开挖施工方案 土方开挖施工方案 编制: 审核: 审批: 藤田(中国)建设工程有限公司 土方开挖施工方案 目 录 一、 编制依据············································1 二、 工程概况············································1 三、 施工方案············································2 四、 进度保证措施········································7 五、 质量保证措施········································8 六、 现场监测及应急措施··································9 七、 安全文明保证措施················
土方开挖施工方案 土方开挖施工方案 编制: 审核: 审批: 藤田(中国)建设工程有限公司 土方开挖施工方案 目 录 一、 编制依据············································1 二、 工程概况············································1 三、 施工方案············································2 四、 进度保证措施········································7 五、 质量保证措施········································8 六、 现场监测及应急措施··································9 七、 安全文明保证措施················